Data centre development continues to advance, and the regulation thereof follows apace across Canada. We previously detailed the fundamentals of data centre legal frameworks here. Four major power plants intended to serve data centres have now been approved in Alberta,1 and as of last week the province proposed an entirely new regime which will provide additional clarity on the regulatory process. Over the summer, other developments occurred in Alberta, Ontario and federally. All are summarized below.
Latest Developments in Alberta: Bill 42 and Alberta Utilities Commission Regulation
On November 18, 2026, the Alberta government tabled legislation, Bill 42, which, among other consequential changes to energy, environment and forestry regulatory frameworks, creates a new framework for data centre approvals:
- Making the Alberta Utilities Commission (AUC) the regulator for data centre systems above a prescribed threshold (expected to be 10 megawatts (MW)) – for the purposes of this comment, “data centre” refers to the combined computing and power-generation facilities that comprise a data centre system. This requires a new kind of application for data centre developers but allows data centres to override municipal approvals as power developers can.
- Allowing large, designated data centres to self-supply electricity across multiple differently owned properties, particularly at transmission voltage.
- Creating a framework for future public interest restrictions on data centre development, including setbacks from residences, prohibitions on use of agricultural land, minimization of water use and other operational requirements. These restrictions will be specified in future regulations or AUC rules.
All of these provisions will come into force on proclamation, suggesting a potential intention to develop relevant regulations before these provisions apply.
Alongside these legislative changes, the provincial electric system operator, the Alberta Electric System Operator (AESO), continues to develop its approach to large load integration, with consultation expected to restart this fall.2
A New Regulator for Data Centres: The Alberta Utilities Commission
An approval from the AUC, which currently regulates electric power plants and public utilities (but not data centres), will be required for every data centre above a threshold.3 The Alberta government has indicated that this threshold will be 10 MW. On considering whether the public interest is met by an application for an approval, the AUC cannot consider the computing activities carried out by the data centre or how its data is used.4 This limitation appears to be intended keep the AUC to its traditional mandate of physical infrastructure and electricity/utility concerns. We expect therefore that considerations for data centre applications will be similar to those the AUC applies to power plants – noise, impacts to nearby properties, air emissions, etc. The AUC has demonstrated it can effectively apply these considerations to data centre power plants already in its recent rejection of Synapse Real Estate Corp.’s data centre proposal in Olds, as we discussed in a previous comment.
Data centres which are at a prescribed point of construction prior to the coming into force of these provisions will be deemed to have an AUC approval.
One of the most consequential impacts of AUC jurisdiction over data centres is that section 619 of the Municipal Government Act5 will now apply to data centres. Section 619 provides that AUC approvals prevail over municipal authorizations and municipalities have to issue authorizations consistent with those AUC approvals. This power could be important given some municipal opposition to data centre development.6
Designated Data Centres: Self Supply and Transmission
While all data centres above the threshold must be approved by the AUC, large data centres can make a further application for designation as a designated data centre. This designation supports electricity self supply, particularly through high-voltage transmission lines suitable for large projects.
In order to be designated, the data centre and designation must:
- ensure that all transmission facility costs associated with the data centre system are to be wholly paid by the owners of the data centre system;
- support the efficient exchange of electric energy with the grid;
- based on the AESO’s assessment, maintain or improve the reliability and adequacy of the interconnected electric system – this assessment is a novel requirement for industrial connections;
- contain at least one generating unit; and
- have a maximum demand directly from the transmission system that is either: equal to or greater than 75 megawatts; or less than 75 megawatts as established by the AESO.
A designation can be subject to any terms and conditions the AUC considers appropriate.7
Designated data centres then have all their power exempt from restrictions against self-supply while exporting to the grid.8 This will allow these designated data centre systems to self-supply across multiple properties with different ownerships.
Developers can build transmission lines in designated data centres without the usual approvals and without having to apply for approval of transmission rates.9 This framework will allow for all parties, potentially including incumbent transmission facility owners (AltaLink, ATCO, ENMAX, EPCOR) to develop data centre transmission lines, with costs to be borne only by the data centre and not Albertan customers.10 The AESO can use the transmission facilities of a designated data centre to provide system access service, as approved by the AUC.11
Agricultural Land and Setbacks – New Restrictions to Come
Any data centre on designated high-quality agricultural land must be approved by the Lieutenant Governor in Council, the provincial cabinet.12 This restriction applies only until 2027,13 suggesting that more permanent regulations will be developed by then.
The Lieutenant Governor in Council can make further regulations specifying the high-quality agricultural land requiring cabinet approval to build on and setbacks for data centres, as well as restrictions around water use.14 The Alberta government has indicated that these restrictions will include:
- preventing data centres being built within 600 metres of the nearest home;
- prohibiting data centres on Class 1 and 2 agricultural lands, as well as Class 3 land in municipalities without Class 1 or 2 land, and large data centres on irrigated farm land. In certain circumstances, alternative setbacks could be set by municipalities where local planning supports compatible development; and
- a provincewide water use standard to bring data centres’ cooling water use close to zero, while requiring that data centres be designed and operated so excess heat can be recovered and made available for greenhouses, industry or homes.15
Initial Data Centre Regulation
The new AUC regulatory framework operates beside Alberta’s initial Data Centre Regulation,16 enacted on June 9, 2026. The Data Centre Regulation focuses on the effects of data centres on the grid and primarily empowers the AESO to support data centres to bring their own generation or energy storage. The AESO will further develop this framework through Independent System Operator Rules.
Data centres that bring their own generation are referred to as “tethered data centres.” Tethered data centres must not have a maximum load higher than the generation or energy storage they are tethered to, and these projects must generally proceed together through the interconnection process.17 The generation or energy storage for tethered data centres must be new or a new category of “underutilized generation and storage.”18 In circumstances where the AESO considers it appropriate, a data centre can connect up to three years in advance of its tethered generation or energy storage, as what is called a “bridged data centre.”19
In exchange for these restrictions, tethered data centres are to be given priority in interconnection.20 In fact, given capacity limitations, it is likely that only tethered data centres will be able to be connected to Alberta’s grid in coming years. The AESO will also be required to restrict power to bridged data centres and large data centres first in situations of constrained power supply and load shedding.21
The AESO has also indicated that, initially at least, only natural gas-fired generation may be eligible to support tethered data centres, though as noted, those regulations are still being developed and may be impacted by the new frameworks in Bill 42.22
Ontario – Data Centre Playbook
On August 13, 2026, the Ontario Government released a draft framework for its Data Centre Playbook. The Data Centre Playbook Framework provides a high-level overview of how Ontario will approach data centre development, including the Province’s use of the discretion over data centre electricity connections which it gave itself under Bill 40, the Protect Ontario by Securing Affordable Energy for Generations Act, 2025, as we previously discussed.
The Data Centre Framework is detailed in the press release for the Framework, a media backgrounder, and an official posting in the Environmental Registry of Ontario on which the government consulted with the public.
Data Centre Playbook Elements Consulted On
Ontario consulted on two main elements of the Data Centre Playbook: a “Strategic Priority Assessment” and a new electricity rate for data centres. Consultation on these elements of the Data Centre Playbook closed on September 12, 2026.
The Data Centre Playbook’s primary innovation is a new three pillar “Strategic Priority Assessment” to be applied alongside existing regulatory and electricity interconnection processes. The Strategic Priority Assessment would determine whether proposed data centres:
- Pillar 1: Advance Economic Development: This assessment would be focused on economic benefits within Ontario, in terms of jobs, growing local (and Canadian) supply chains, bringing in investment and government revenue, and helping Ontario businesses be more productive.
- Pillar 2: Protect Data Security and Digital Sovereignty: Proposed data centres would be expected to advance Ontario’s and/or Canada’s control over high sensitivity and critical data, and digital infrastructure, in line with Ontarian digital sovereignty and cyber security policies, and, “where possible”, those of Canada. Ontario would prefer Canadian-owned and operated data centres.
- Pillar 3: Invest in Communities and Earn Public Trust: This assessment would consider community benefits, including training and employment, community engagement, and local technical, fiscal and environmental effects.
In addition to the new three pillar assessment, the Data Centre Playbook also proposes a new rate class for data centres, potentially down to those as small as 1 MW. This rate class would potentially not be eligible for the current Industrial Conservation Initiative (ICI). The ICI allows some large industrial consumers to be charged the largest portion of their electricity bill (the Global Adjustment) on demand during peak demand hours rather than all hours. The press release and media backgrounder also suggest that a new data centre rate class could be charged a higher rate overall and that the purpose for this higher rate is to ensure that data centres pay for the cost of their impact on the electricity system.
Data Centre Playbook General Policy Commitments
The press release and media backgrounder for the Data Centre Playbook also state that the Government of Ontario:
- May provide non-financial support for data centres, but only non-financial support, such as white glove service and permitting facilitation;
- May consider proponent plans to bring their own power; and
- Will prioritize data centres that use closed-loop water systems and other cutting edge noise reduction and heat recovery technologies.
These policy commitments and the Data Centre Playbook position Ontario to speed up the approval of data centres which support provincial policy objectives.
Canada
On September 3, 2026, the Government of Canada announced a voluntary framework for data centre development signed onto by 23 data centre developers, including the largest players such as Amazon Web Services, Anthropic, Google, Meta and Microsoft; and the Federation of Canadian Municipalities. “Canada’s Responsible Data Centre Development Principles” largely mirror the considerations of Ontario’s Data Centre Playbook, with five principles:
- Data centres must create lasting local benefits.
- Data centres must not shift electricity costs to Canadians.
- Data centres must minimize water use and environmental impacts.
- Data centres must be transparent about local impacts.
- Data centres must bring strategic value to Canada.
Canada’s Responsible Data Centre Development Principles are meant to be complementary to provincial, territorial and municipal regulatory oversight, as the Government of Canada recognizes that it does not have a federal approval role.23
1 AUC Decision 30261-D02-2026, Greenlight Electricity Centre GP Ltd. Greenlight Electricity Centre, Project June 25, 2026; AUC Decision 30518-D01-2026, Heartland Power Generation LP and Northbridge Power GPC Inc. Beacon AI Centers – Heartland Project Thermal Power Plant, October 23, 2026; AUC Decision 30524-D01-2026, Indus Power Generation LP and Northbridge Power GPC Inc. Beacon AI Centers – Indus Project Thermal Power Plant, November 17, 2026; and AUC Decision 30787-D01-2026, Cree Ative Datacenter Corp. Mihta Askiy Data Center Power Plant, November 20, 2026.
2 AESO, “Data Centre Update”, September 2026, online: AESO Data Centre Update.
3 Hydro and Electric Energy Act, RSA 2000 ch-16, new s. 11.1(2) (HEEA).
4 HEEA, new s. 2(b.1).
5 RSA 2000, c M-26.
6 See for instance the temporary moratorium enacted by Rocky View County and new restrictions considered by the City of Calgary: CBC, “Calgary councillors want power to pause mega-scale data centre development”, November 18, 2026, online: Calgary councillors want power to pause mega-scale data centre development | CBC News.
7 HEEA, new s. 4.1.
8 Electric Utilities Act, SA 2003 cE-5.1, new s. 2(1)(b.2) (EUA).
9 EUA, new ss. 1(1)(z), 30(3)(a), and 37(2).
10 EUA, new ss. 30(2.1), 37(2), and 37.1.
11 EUA, new 40.1.
12 HEEA, new s. 11.1(2).
13 HEEA, new s. 11.1(7).
14 HEEA, new s. 11.1(5).
15 Government of Alberta, “New restrictions on data centres”, November 18, 2026, online: New restrictions on data centres | alberta.ca.
16 Alta Reg 117/2026.
17 Data Centre Regulation, ss. 5 and 8.
18 Data Centre Regulation, ss. 4-5.
19 Data Centre Regulation, s. 9.
20 Data Centre Regulation, s. 6.
21 Data Centre Regulation, s. 10.
22 AESO, Large Load Integration Phase 2A, Proposed BYOG Process, June 26, 2026, PDF 4 of 29, online: Proposed BYOG Process.
23 CBC News, Benjamin Lopez Steven, “Want to build a data centre in Canada? These are the federal government’s new expectations”, September 3, 2026, online: Want to build a data centre in Canada? These are the federal government’s new expectations | CBC News.